Concrete Estimation: The Foundation of Accurate Bidding
Concrete Volume Calculations
Slab-on-Grade:
Volume (CY) = Length × Width × Thickness ÷ 27
Example: 100' × 50' × 4" = 100 × 50 × 0.333 ÷ 27 = 61.7 CY
Always add 5-10% for waste and topping irregularities.
Footings:
Volume = Total Linear Footage × Width × Depth ÷ 27
Columns:
Volume = π × radius² × height × quantity
Concrete Pricing (2026 National Averages)
Rebar Estimation
Labor Costs